Smurfit WestRock Manufacturing Facility

Power distribution engineering for a new 588,000-square-foot packaging plant, built around three 4,000A 100%-rated 480V services and sized for heavy process loads and continuous operation.

The challenge

A new 588,000-square-foot packaging plant with heavy process loads and continuous operation. One of the harder pieces was a change in the utility company's requirements for the three 4,000A, 100%-rated services feeding the building.

What we did

We engineered three 4,000A, 100%-rated 480V services, and coordinated all feeder conduit in BIM to keep it routed high and outside the ESFR sprinkler clearances. High-bay lighting was designed to hit the required levels under tall ceilings, with individual occupancy-sensor control to manage energy.

One more detail

The facility includes an interior rail line running into the building, allowing train cars to be unloaded inside.

Project facts

Location
Pleasant Prairie, WI
Size
588,000 SF
Services
(3) 4,000A · 480V · 100% rated
Delivery
New build
Notable
Interior rail line

Scope delivered

  • (3) 4,000A 100%-rated 480V services
  • High-bay lighting with occupancy control
  • BIM feeders routed clear of ESFR
  • Interior rail-line power